What a New Detached ADU in Richardson, TX actually involves
A new detached ADU in Richardson, TX typically runs $45,000 – $130,000 and takes four to seven months from survey to final inspection, depending on size and whether utilities have to be trenched from the main house. That number covers a standalone structure on your existing lot: foundation, framing, roof, electrical, plumbing, HVAC, insulation, and finishes. Call (833) 954-4985 and we’ll walk your lot and give you a written, line-item estimate before you commit to anything.
How we build a New Detached ADU, stage by stage

Every detached ADU we build in Richardson follows the same sequence, and the sequence matters because each stage locks in decisions the next one depends on. Here’s what actually happens, and when.
Stage 1: Site survey and feasibility (week 1)
Before anyone draws a thing, we survey the lot. On Richardson’s older platted blocks, lot coverage and setback rules are the first thing that make or break a detached ADU, so we measure your existing footprint against what the city allows. You decide the rough size and where the structure sits. This is also when we flag whether your alley access, side yard, or driveway can carry equipment and concrete trucks without tearing up a fence.
Stage 2: Design, engineering, and permits (weeks 2 – 8)
Once the footprint is set, we produce the drawings and structural engineering and submit for permits. On a detached ADU this stage is the schedule’s wild card: Richardson’s infill posture means plan review and demolition inspection are routine parts of the job here, and how fast your permit moves depends on how complete the submission is the first time. You decide the floor plan and exterior finish package in this window, because those choices go into the permit set.
Stage 3: Site prep, foundation, and utilities (weeks 6 – 10)
After permit issuance we clear the footprint, set the forms, and pour the foundation. If the ADU needs a separate electrical service, gas line, or sewer tie-in, the trenching and inspections happen here. Richardson’s expansive clay soils are the reason we don’t shortcut foundation prep; a slab on poorly compacted clay will move, and a detached structure has no big house to hide behind. You’ll see the foundation inspection before framing starts.
Stage 4: Framing, roof, and rough-in trades (weeks 10 – 18)
Framing, sheathing, and roofing go up in one flow, then electrical, plumbing, and HVAC rough-in follow with their own inspections. This is the stage where North Texas weather dictates the calendar: framing and dry-in get squeezed into spring and fall around summer heat and winter ice, so we build float into the schedule rather than promise a date the weather can break.
Stage 5: Insulation, finishes, and final inspection (weeks 18 – 28)
Insulation, drywall, cabinetry, flooring, fixtures, and paint close it out, followed by the final inspection and a walkthrough with you. You’ll make your finish selections back in Stage 2 so nothing sits idle waiting on a cabinet decision. The whole project is covered by our 730-Day Done Right Promise once we hand over the keys.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll choose between for a detached ADU
Most of the budget swings in a New Detached ADU come from four decisions. Here’s the honest trade-off on each.
- Size and configuration: A studio or one-bedroom ADU lands near the low end of the $45,000 – $130,000 range; a two-bedroom with a full kitchen, laundry, and a covered porch pushes toward the top. Build the size you can rent or house family in, not the biggest footprint the lot allows.
- Exterior cladding: James Hardie fiber cement holds up to North Texas hail and sun and holds paint far longer than wood siding, at a modest premium. Brick veneer matches the ranch homes around you and adds cost and lead time. Vinyl is cheapest and shows its age fastest.
- Cabinetry and finishes: KraftMaid or Wellborn cabinets in the ADU kitchen and a Cambria or quartz counter give you a durable, rentable finish. Builder-grade stock cabinets save real money but read as temporary to a tenant or appraiser.
- Utilities and mechanicals: Tying into the main house’s electrical service is cheaper than a separate meter if your panel has capacity. A separate service costs more upfront but makes the ADU truly independent for rental or family use. Same logic applies to HVAC: a dedicated mini-split system beats extending the house ductwork.
What a New Detached ADU costs in Richardson, TX

Expect $45,000 – $130,000 for a detached ADU here, with the median completed project landing around $80,000 – $95,000 for a one-bedroom with a full kitchen and bath. Five variables push a job from the bottom of that range to the top:
- Square footage: the single biggest lever. Every additional 200 square feet adds roughly $18,000 – $28,000 in foundation, framing, roofing, and finishes.
- Utility runs: trenching a sewer, water, gas, and electrical line across a long yard adds $6,000 – $15,000; a structure sited close to the main house saves most of that.
- Foundation conditions: older Richardson lots with clay movement or a slope may need over-excavation or piers, adding $3,000 – $10,000.
- Material grade: fiber cement and quality cabinetry versus builder-grade moves the finish package by $8,000 – $20,000.
- Permit scope and site work: driveway, walkway, and grading to drain water away from both structures can add $4,000 – $12,000.
A written estimate from us itemizes foundation, framing, roofing, each trade, and the allowance for finishes, so you see where every dollar lands. What it won’t include unless we itemize it: landscaping beyond grading, furniture, and any site work tied to a future project. Upfront pricing, no surprises.
See the difference
Before
After
Before
After
Before
AfterWhat Richardson homes specifically do to this job
Richardson’s construction market runs on two parallel realities, and both touch an ADU build. The mature 1950s – 60s ranch core around Richardson Heights sits on pier-and-beam foundations and narrow original lots, where lot-coverage and setback rules mean fitting a detached structure in the backyard takes a real survey before anyone draws. The massive Telecom Corridor footprint at CityLine and Palisades keeps the city’s inspection and permitting pipeline busy year-round, so a complete, well-prepared permit submission is what keeps your ADU moving instead of sitting in review. The clay soils and spring hail that drive foundation piering and post-storm roof replacements across Richardson shape how we detail a detached structure too: a proper slab, drainage away from both buildings, and hail-rated roofing. If your ADU project is part of a full Home Additions & ADU in Richardson plan, we scope both together so the site work isn’t done twice.
Serving Richardson, TX – Our Local Coverage Area
We serve Richardson and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – New Detached ADU in Richardson

Plan on four to seven months from signed contract to final inspection, with permitting alone taking six to ten weeks on the front end. A one-bedroom structure close to the main house usually lands near four to five months; a two-bedroom with long utility runs and a separate electrical service runs longer. Call (833) 954-4985 and we’ll give you a schedule tied to your lot.
Yes. A detached ADU requires building, electrical, plumbing, and mechanical permits plus plan review, and we handle the submission and inspections as part of the job. Because Richardson processes a steady stream of infill and addition permits, a complete submission is what keeps your project from stalling in review.
Often yes, if the ADU sits close enough to the main house and your electrical panel has spare capacity. A separate service and independent meter costs more but leaves the main house untouched and makes the ADU easier to rent. We evaluate your panel and existing lines during the site survey and price both options.
Our range is $45,000 – $130,000, with most one-bedroom builds landing around $80,000 – $95,000. Size, utility runs, foundation conditions, and finish grade are what move the number. Call (833) 954-4985 for a free on-site estimate with a line-item quote.
Every ADU we build is covered by our 730-Day Done Right Promise: if it’s not done right, we make it right. Calls are answered by a live person 24/7, and our technicians have up to 12 years of experience. You’ll have a written workmanship warranty in hand at walkthrough.
Get a free estimate for your New Detached ADU in Richardson
We’ll come out, walk your lot, check setbacks and utility routes, and give you a written, line-item estimate for a New Detached ADU in Richardson with no obligation. Call (833) 954-4985 to schedule. On that call we’ll ask about your lot, your target size, and how you plan to use the ADU, then set a time to walk the property. Homeowners often pair this with Concrete Driveways & Concrete Work in Richardson or Paver Driveways in Richardson once the site plan takes shape. We also handle the wider scope through our Home Additions & ADU service across Richardson.
Written by the team at Groundwork Construction Co.