ADU Site Prep & Utilities in McKinney: What the Work Actually Involves
ADU site prep & utilities in McKinney runs $45,000 – $130,000 for the groundwork and service work alone, before the structure itself, and typically takes 4 – 8 weeks from first stake in the ground to final utility inspection. That covers grading and excavation, the slab or pier-and-beam foundation, water and sewer tie-ins, the electrical service run, and gas if you’re extending it. Call (833) 954-4985 and we’ll walk your lot, check the utility map, and put a real number on paper.
What We Do First, Third, and Last on a McKinney ADU Site

Site prep and utilities aren’t one job, they’re a sequence, and the order matters more than most homeowners expect. Here’s how it runs on a McKinney lot.
Stage 1: Utility locate and survey (days 1 – 3). Before anything gets dug, we call in the locate service and confirm where the existing water, sewer, gas, and electric actually run. On the north side out in 75070 and 75071, that’s usually clean because the subdivisions were platted with recorded easements. Downtown in 75069 it’s a different animal: old service laterals that don’t match the plat, sometimes a shared line. You decide here whether we tie into the existing service or pull a new meter, and that decision sets the electrical and water budget.
Stage 2: Excavation and grading (days 3 – 8). We strip topsoil, cut the pad to grade, and shape the drainage so water moves away from both the ADU and the main house. Expansive clay is the whole story here. You’ll decide whether you want a post-tension slab or a pier-and-beam foundation, and that call is driven by soil test results, not preference.
Stage 3: Foundation (days 8 – 18). Form, rebar or post-tension cable, inspection, pour, cure. Concrete cure time in a McKinney July is a real scheduling item, not a formality.
Stage 4: Rough utilities (days 18 – 30). Sewer trench and lateral to the tie-in point, water line, electric conduit from the meter or main panel, gas line if you’re running it. This is the stage where a sewer line that has to cross an existing driveway or a mature pecan tree changes the price fast.
Stage 5: Inspections and backfill (days 30 – 40+). Rough plumbing and electrical inspections, then backfill, compaction, and final grade. You get a written punch list and the inspection sign-offs in hand.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Site and Utility Choices You’ll Make
These are the decisions that move your number, and the honest trade-off on each.
- Foundation type. Post-tension slab is faster and cheaper on flat, well-drained lots in the newer subdivisions. Pier-and-beam costs more upfront but handles the clay movement better and gives you access to plumbing underneath, which matters on infill lots near the historic core.
- Electrical service. Tying into your existing panel is cheaper if there’s capacity. A separate meter means a second monthly bill but keeps the ADU easy to rent or hand to family.
- Sewer tie-in. Gravity lateral to the existing line is straightforward. If grade won’t cooperate, a lift pump adds cost and a maintenance item you should know about before you commit.
- Grading and drainage. Basic slope-away grading is included. French drains, retaining, or a swale to redirect runoff from a neighboring lot is extra, and on tight downtown lots it’s often necessary.
- Utility trench depth and conduit. Direct-burial cable is the cheap route. Conduit costs more and lets you pull new wire later without digging. For a structure you plan to keep for decades, conduit is the better buy.
Where the ADU ties into siding or trim, we spec James Hardie because it holds up to North Texas sun and hail without the repaint cycle wood demands.
What ADU Site Prep & Utilities Costs in McKinney, TX

Plan on $45,000 – $130,000 for site prep and utilities on a McKinney ADU, with most jobs landing between $60,000 and $95,000. Site prep and utilities is a slice of the full Home Additions & ADU in McKinney budget, which runs $90,000 – $220,000 once the structure is included. Five things push a job toward the top of that range.
- Lot condition. A flat, cleared lot in a newer 75071 subdivision sits at the low end. A sloped or tree-heavy downtown lot needing retaining and extra grading runs high.
- Distance to utilities. Every extra foot of trench to reach the sewer main or the panel adds cost. Corner lots and deep setbacks pay for it.
- Utility relocation. Moving an existing line, meter, or easement is the single biggest surprise line item.
- Tie-in complexity. Gravity sewer is cheap; a lift pump or a long water run is not.
- Permit scope. Historic district review in the 75069 core can add weeks and a design review fee a subdivision lot never sees.
Your written estimate lists excavation, foundation, utility runs, inspections, and backfill line by line. It doesn’t cover the ADU structure itself, finishes, or landscaping beyond final grade. Upfront pricing means the number you see is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhat McKinney Lots Specifically Do to This Job
McKinney’s growth pattern makes this job two different projects depending on which ZIP you’re in. Out in 75070 and 75071, you’re working greenfield subdivision lots platted with clean easements and fast-track permitting, so site prep moves predictably. Downtown in 75069, new construction sits blocks from century-old homes, and the Historic Preservation Advisory Board reviews exterior changes to contributing structures. That review can add weeks, and on infill lots we routinely find old service laterals that don’t match the recorded plat. The clay underneath both is the same: expansive soil that swells and shrinks with our wet-dry cycles, which is why post-tension slabs and pier-and-beam leveling are routine here and why we pour early in the morning when summer pushes past 100°F. Homeowners in Stonebridge Ranch and around the downtown square both end up asking the same question about drainage, and both deserve a real answer before we break ground.
Serving McKinney, TX – Our Local Coverage Area
We serve McKinney and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: ADU Site Prep & Utilities in McKinney

Four to eight weeks from first stake to final utility inspection, with downtown 75069 permits often running longest because of historic review. Call (833) 954-4985 for a timeline built around your lot.
Yes. Grading, foundation, plumbing, and electrical each require separate permits and inspections. We pull them and pass them, and we hand you the sign-offs.
Sometimes, if the existing service has capacity and grade cooperates. Often it can’t, especially downtown where old laterals and clay movement force a new tie-in.
$45,000 – $130,000, with most jobs between $60,000 and $95,000. Call (833) 954-4985 for an exact quote. Estimates are free.
Every job is backed by our 730-Day Done Right Promise. If it’s not done right, we make it right.
Get a Free Site Prep & Utilities Estimate in McKinney
Call (833) 954-4985 and a live person answers, day or night. We’ll schedule a free on-site walk of your lot, check the utility map, and follow up with a written, line-item estimate for the site prep and utilities. Many homeowners pair the groundwork with a new Concrete Driveways & Concrete Work in McKinney or Paver Driveways in McKinney project while the equipment is already on site. See our Home Additions & ADU service and our McKinney coverage area to plan the rest.
Written by the team at Groundwork Construction Co.