Chain Link Fence in Garland, TX: What the Job Actually Involves
A chain link fence in Garland typically runs $3,500 to $9,000 for a standard residential lot, and most jobs are finished in two to four working days. You’re getting galvanized or vinyl-coated steel fabric stretched over posts set in concrete, with framework, gates, and terminal hardware included. The cost depends on linear footage, height, gauge, and how much clearing the fence line needs before anyone digs. For an exact number on your property, call (833) 954-4985 and we’ll walk the line with you.
How We Build a Chain Link Fence in Garland, Start to Finish

Every job follows the same sequence. Here’s what actually happens, day by day, so you know what to expect and when you’ll be asked to make a call.
Stage 1: The walkthrough and line layout (day one, about an hour)
We meet you on the property, walk the proposed fence line, and mark it with stakes and string. This is where you confirm exact placement, gate locations, and height. If the line crosses a utility easement or runs close to a property boundary, we flag it now rather than after the concrete sets. You’ll also sign off on fabric gauge and post spacing at this visit, since both are locked in before we order material.
Stage 2: Utility locate and line clearing (one to three days of waiting)
We call in the Texas utility locate before any digging. That takes a few days to clear, and it’s non-negotiable – a post-hole shovel doesn’t know where the gas line sits. Meanwhile, you handle brush, old fence removal, or anything sitting in the path. If there’s an existing fence to tear out, that’s a separate line item and usually a half-day of work with a trailer haul-off.
Stage 3: Setting posts (day one or two of actual build, four to six hours)
Holes get dug to depth, terminal posts and line posts are set, and everything gets concrete. On Garland’s blackland clay, hole depth and concrete volume matter more than they would in sand – the soil shrinks and swells hard, so we set deeper and backfill properly. Nothing above ground gets attached until the concrete cures, usually overnight.
Stage 4: Stretching fabric and hanging gates (day two or three, most of a day)
Top rail goes on, tension bands and fabric get pulled taut with a stretcher bar, and gates hang on their hinges. You’ll test the swing and latch with us before we leave. A chain link gate that drags or sags is a hardware problem, not a fabric problem, so this is the check that catches it.
Stage 5: Final walk and cleanup (same day, an hour)
We tighten hardware, clip the fabric to the tension wire, haul off leftover material, and walk the line with you. Any post that needs a second look gets noted on the spot. From first call to finished fence, plan on about a week and a half, with the build itself eating only two to four days of that.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Chain Link Options You’ll Choose Between
Chain link isn’t one product. The choices below are the ones that actually change the number and how long the fence lasts in North Texas weather.
- Fabric gauge: 11-gauge is the lighter residential standard and costs less; 9-gauge is noticeably heavier and harder to cut or bend by accident. On a fence line that sees dogs leaning on it or kids climbing it, 9-gauge earns its extra cost.
- Coating: Bare galvanized steel is the cheapest and holds up fine, but it shows a dull gray after a few seasons. Vinyl-coated fabric – green and black are the common picks – runs more and keeps its color, which matters if the fence faces the street.
- Height: Four feet is fine for a pet boundary, five is the residential default, and six or higher gets used where security or privacy from a sightline is the goal. Height drives post spacing and cost per foot.
- Post and rail weight: Standard weight posts versus heavier schedule-40 pipe. The heavier pipe resists bending from a mower or a car door and is the better pick on a corner lot with tight clearance.
- Gate hardware: Self-closing hinges, drop rods, and latches range from plain to heavy-duty. A wide driveway gate needs a heavier frame and a different hinge than a three-foot walk gate.
- Top rail and tension wire: A tension wire along the bottom keeps the fabric from lifting; it’s cheap and worth adding. Top rail is standard on residential runs.
Brands matter less here than spec, but where a heavier pipe frame or a specific coating line is the right fit, we specify it in writing so you’re comparing the same thing across bids. Our technicians have up to 12 years of experience, and they’ll tell you plainly when the cheaper gauge is the honest choice.
What a Chain Link Fence Costs in Garland, TX

For a typical Garland lot, plan on $3,500 to $9,000. That price band covers material, labor, concrete, and cleanup. Where you land inside it comes down to five things:
- Linear footage: The single biggest driver. A small backyard enclosure and a full property perimeter are different jobs entirely.
- Height and gauge: Moving from four-foot 11-gauge to six-foot 9-gauge can add meaningful cost per foot, especially on a long run.
- Existing fence removal: Tear-out and haul-off is a separate line item, usually a few hundred dollars depending on length and how the old posts are set.
- Line condition: Clearing brush, cutting roots, or working around a shed or mature tree adds prep time. The pecan and oak canopies common near downtown Garland push roots right into fence lines.
- Gates and hardware: Each gate is priced on its own, and a wide double gate with heavier hardware adds more than a walk gate.
A written estimate from us lists footage, height, gauge, coating, gate count and size, post spacing, removal, and haul-off so you can see exactly what you’re paying for. What it won’t include unless you ask: stump grinding, fence staining (not applicable to chain link), or landscaping repair along the line. Our pricing is upfront – the number you see is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhat Garland Homes Specifically Do to This Job
Garland went up in a handful of postwar booms – the 1950s and 60s core around downtown, then the 1970s and 80s ranch sprawl out toward Rowlett and Sachse. That means almost every fence we build here replaces an older one on a mid-century slab lot, not a fresh install on an empty lot. In the 75040 and 75041 ZIP codes, mature pecan and oak canopies sit close to fence lines, and roots from those trees are the most common reason a post won’t drive where the layout wants it. On the 75042 side, ranch lots with detached garages often need a gate placed to keep driveway access clear, which changes the corner layout. Clay soil is the other constant: it expands and contracts hard through hot summers and wet winters, so posts set too shallow will lean within a season. We plan for that at the hole stage, not after. Garland doesn’t issue a routine permit for a standard residential chain link fence, but HOA rules and utility easements along the property line still apply, and we’ll tell you what to confirm before we break ground.
This work often runs alongside a bigger project. If you’re already reworking the yard, it’s worth looking at Fence Installation in Garland as part of a full property plan, and homeowners often pair a new fence with Door Installation in Garland when a gate or back entry is part of the scope.
Serving Garland, TX – Our Local Coverage Area
We serve Garland and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Chain Link Fence in Garland

Most jobs are finished in two to four working days once construction starts, with the utility locate adding a few days of waiting beforehand. Plan on about a week and a half from first call to finished fence. Call (833) 954-4985 for a timeline built around your specific lot.
Standard residential chain link typically doesn’t require a permit, but HOA rules and utility easements along the property line still apply. We’ll tell you what to confirm with your HOA before we order material. Call (833) 954-4985 and we’ll walk you through it.
Expect $3,500 to $9,000 for a typical residential lot, driven by footage, height, gauge, coating, and gate count. Removal of an old fence is a separate line item. Call (833) 954-4985 for an exact quote – estimates are free.
Almost always, yes. We call in the utility locate first and lay out the line around existing plumbing and structures, so digging stays where it’s safe. If the layout has to shift, we flag it before the concrete goes in. Call (833) 954-4985 to talk through your property.
Yes – every fence we build is covered by our 730-Day Done Right Promise, one of the longest workmanship guarantees in residential construction: if it isn’t done right, we make it right. Hardware and material defects are covered under the same commitment. Call (833) 954-4985 to start with a free estimate.
Get a Free Chain Link Fence Estimate in Garland
If you’re ready to price a chain link fence in Garland, call (833) 954-4985 and a live person will answer – any hour, any day. Tell us the footage and what you’re enclosing, and we’ll set a walkthrough. You’ll get a written line-item estimate, upfront pricing with no surprises, and a look at 0% financing for 18 months. Whether it’s a pet run or a full perimeter, you’ll know exactly what it costs before we dig a single hole.